Managers#
This chapter is for whoever decides what gets done, answers for what it cost, and runs the meetings where both are settled. It assumes Developers: the states, the roles, the clock and the deadlines are described there, and here they are used.
The chapter begins with running a project: its settings, who does the work of each category, what you can do to many issues at once, and the new reports waiting for a decision. Then come the work that comes back on a schedule, meetings and the standing meeting, the plan and what it tells you, releases, and the money: work packages, timesheets, the reports to a funder, and what you may and may not do with all of it.
Running a project#
Figure 20 Manage: the projects, their status and who is in them.#
A project is administered in tabs. Under the administration bar
(Users, Projects, Tags, …) comes the project’s name, and under that the
project’s own bar: Edit Project, Categories, Versions, Periodic
tasks, Jour fixes, and Work packages where the project runs the
compliance process. The first bar is the installation, the second is
this project, and the name between them says which project you are in.
Edit Project is the project itself: its name, status, visibility and
description, the subprojects, the custom-field links and the
membership, with locust’s own settings beside MantisBT’s. The lists
that are kept on their own are on the other tabs, and when you add a
category or a version, you come back to its tab.
The project’s settings#
Figure 21 A project’s settings: MantisBT’s above, locust’s own below.#
These are the settings that change how the project works:
Compliance processRuns the project on the process with ten states and six roles, instead of MantisBT’s seven statuses. Everything else in Developers depends on this switch. It can be turned on for one project and left off for the rest.
Verifier is not the implementerSomebody other than the implementer always does the control. This setting requires the same for the verification.
Default communicatorA new issue of this project starts with this person as its communicator, so the field is filled from the beginning.
Allow fast-trackLets an issue of trivial or text severity skip the control, the release and the deployment. See Developers. Note that in such a project, lowering an existing issue’s severity into that range is deliberately the management’s decision alone.
Effort estimatesOffers an estimated effort in hours on this project’s issues. A compliance project always has them. A plain project can have them, and without them the Gantt chart has nothing to draw.
Deadline window (days)How many days before its due date an issue begins to rise in the priority queue. The default is fourteen. With zero, a deadline raises an issue only once it has passed.
Report Stay boxWhether the report form offers the box that brings a reporter back to the form after each report.
Require 2FA fromThe access level from which members must have two-factor authentication in force. Setting it lowers the stored level of the members who do not have it. They cannot be promoted back until they set it up, and after that a manager has to raise their level again. When a member loses their device, an administrator can deactivate their one-time code (Administrators).
Estimate before implementingAn issue of this project enters
implementingonly with an estimated effort, because that is the point at which the plan is finished. Closing needs no estimate: an issue that turns out not to be work cannot be estimated either.Classify before workingNobody starts work on an issue of this project without a work package, and no hour of it reaches a sheet unclassified. See Work packages and budgets.
What the process adds in the GanttThe shares that the Gantt chart adds to an estimate for the steps that the estimate does not include: control, verification, deployment, release and communication. The defaults are 15, 15, 5, 5 and 5 per cent.
Keep unclassified hours forHow many years the hours that were recorded without a work package are kept before
locust retaindeletes them (Administrators). Empty keeps them until somebody deletes them.Show times of daySwitched off, the project’s pages, its interface for other programs and its exports show the date of everything that belongs to its issues, and not the time of day. The database keeps the exact times.
There is no switch for a simpler report form; a list sets it. The project’s
bug_report_page_fields says which optional fields the report form
shows, and a project that drops priority, platform, OS, handler and
target version from it asks a newcomer for four things instead of a
dozen. An administrator sets it (Administrators), and the fields
that it hides take their defaults when a report is submitted.
Who does a category’s work#
Most categories name a component. A few name work across several
components instead, such as a specification or a change on every
platform, and an issue there is usually a parent with one child for
each component that has to change. Tick Spans components on such a
category’s page. The tick changes nothing in the tracker itself: it
tells agents where a parent issue belongs (Integrators).
In a project that runs the compliance process, a category’s page
(Categories, then Edit) has a grid under MantisBT’s single Assign
To. It has a row for each person whom the project offers for an
assignment, apart from administrator accounts, and a column for each
role: implementer, reviewer, release signer, deployer and verifier. A
cell has a box only where that person may end that role’s phase. The
communicator has no column, because telling the customers and the
authorities is the job of the project’s Default communicator.
Each box has three states, and a click moves it from one to the next:
- Checked
The person does this kind of work: new issues are given to them automatically, and they may take the role by hand.
- Half-checked
The person may take the role on the category’s issues by hand, and is never given it automatically. Use it for the people who may help out without being where the work goes by default.
- Unchecked
Once anybody in the column is checked or half-checked, the person may not hold that role on the category’s issues.
A column in which nobody is ticked leaves the role to the access level, as before: anybody who may end the phase may take it. So a column is a restriction only once you tick somebody in it. The managers of the project may hold every role, ticked or not.
Figure 22 A category of a compliance project and who does its work. The dash is the half state: Florian Dold may sign this category’s releases and is never the one whom a new issue is given to.#
Every new issue of the category then gets one of the checked people for each role that it leaves empty, whether it is filed from the report form, through REST, by an agent or from a template. Where several people are checked for a role, the issue gets the one who would finish that step first in the project’s plan, the Gantt chart, with everybody’s calendar and share of a day. Where the plan cannot tell them apart, because nothing is estimated, it gets the one who is named in that role on fewer open issues, and after that the first by account name. The reviewer is never the implementer, and the verifier is not the implementer either where the project asks for that. A role that the filing names already, as a template’s issue can, is kept where the category’s column allows that person, and is otherwise chosen like an empty one; the template’s page marks such a person. A release (see Release management) gets no roles this way. The history of the new issue says who was named, the issue page shows each of them from their role’s phase on, and the update page changes them.
A person who is ticked and has since lost the level or the membership
stays in the grid, ticked, with a line that says so, so that you can
take the tick away; meanwhile, new issues pass them over. The
Categories tab lists the people of each category in a Teams column,
the checked ones in bold and the half-checked ones in normal type. If
two managers edit one grid at the same time, each keeps the boxes that
they changed.
Where a column names anybody, it holds on every way in which a person
comes to hold the role: the update page offers only the people that the
column allows, Take this phase, Start timer and Lock are offered
only to them, a mass Update process role and the REST API refuse
anybody else, and a developer whom the column does not allow cannot
move the issue out of the phase, because the move records them as
having done it. Somebody who held the role before you ticked others
keeps it and may finish the phase; the next time the role is given, the
column decides.
One column is different. Release signed by is the one column with a
box for every developer, because there a tick, checked or half-checked,
is itself a permission.
Signing a release means putting an issue into deploying, and it is the
management’s right. A developer who is ticked in that column may sign
the releases of this category’s issues as well: on the issue page, on
the update form, through REST and in a mass action alike. Nobody else
gains anything, an issue of another category still needs a manager, and
a tick whose holder has lost the level grants nothing. Use the column
for a kind of change that a team releases on its own, such as the
documentation or a component that one team owns, and leave it to the
managers everywhere else. The grant follows the issue’s category, so
whoever may change an issue’s category may move the issue into a
category that lets them sign. The history shows both steps.
Many issues at once#
When you select issues in the issue list, the list of actions offers five of locust’s own after MantisBT’s. An action is offered only where at least one project in the list uses the feature that the action is about, and where you have the right that the action needs in that project. Each action checks every issue by the rule that the issue’s own page applies, writes the ones that pass, and lists the others with the reason. A form that cannot be carried out at all, because no meeting, no package or no role was chosen, comes back with your selection and your choice still in it.
MantisBT’s own actions that change the status, Close, Resolve and
Update Status, follow the same rule in a project that runs the
process. Each issue must pass what its update page asks of that move:
an authority that must be told has been told, the plan is finished, the
estimate is there where the project asks for one, and an issue that
ends without a change has a resolution other than “open” and a note in
the action that says why. An issue that fails is listed with the
reason, and the others move.
Figure 23 Discuss for two selected issues, with the project’s next planned
meeting chosen; the list holds its other meetings, each with its
state.#
Update fast-trackTicks or clears the shortcut. A tick is refused for an issue whose severity does not allow it, or whose project does not offer the shortcut. Clearing is open to whoever may update the issue.
DiscussProposes the issues for the agenda of a planned meeting (see Meetings), or records them as discussed at a meeting in any state. Where you run the meeting, the issues go straight onto its agenda. Otherwise they are proposed to whoever runs it, who gets one mail for all of them. An issue that is already on the agenda is passed over, an issue that came out of the meeting is not recorded again, and recording needs the right to update the issue.
Update work packagesAdds one package (see Work packages and budgets) to each issue, or takes it off. An issue can carry several packages, so this action never replaces the packages that an issue already has. A package of another project is refused for that issue.
Update process roleNames one person, or nobody, for one of the six roles. It is refused where the project does not run the process, where the person may not handle issues there, and where it would make the implementer the reviewer (or the verifier, where the project separates that too).
Distribute by workloadChooses the people for the roles of each issue’s current phase and of the phases still to come, from its category’s teams, the same way as a new issue’s people are chosen. It takes the issues in the order that the plan does (deadline, priority, severity, age), so that ten issues are shared out instead of all going to whoever is free today. It asks how: fill only the roles nobody holds, the default, or choose again for every role still to come, whoever holds it now. Choosing again is for when a category’s team has changed, for example, or when the plan made at filing is out of date. Even when choosing again, it keeps three people: the person of a role whose phase is over, the person of the current phase while somebody has the issue locked, and the person of a role for which the team names nobody. A selection from several projects is planned project by project, each against its own plan. An issue of a project that does not run the process is named in the answer and left alone.
New issues#
New issues is a box on your My View that lists everything still in
new that you can see, in the project chosen at the top of the page.
Deciding whether a report is real is the management’s job, so the box is
drawn only for somebody who may manage at least one of the projects
chosen there. Its heading is a link into the issue list that it counts.
It stands just above Unassigned, the other list of work that nobody
has taken on yet, and moves with it. It is a box like the others, and
an installation may give it a place of its own or switch it off in
my_view_boxes. Only a 0 switches off one of the boxes
that locust adds. A map that does not name such a box at all, for
example one taken over from MantisBT or one that an older locust wrote,
leaves the box at its default.
Work that comes back#
Some work comes back on a schedule: the backup check every week, the restore test every quarter, the year-end closing. Filing those by hand means remembering them, and a tracker whose point is that nothing is forgotten should not depend on somebody’s memory.
Figure 24 Periodic tasks: a template, a schedule, and what each one has filed.#
A periodic task is a schedule that files one template by name. The template is the content: an issue whose reporting is already done, with its children, its roles, its estimate, its deadline and its tags. Templates have their own menu (Developers), where any developer writes them. The task is only the schedule, and the schedule is yours to set. Two tasks may file one template, and a template that no task files is filed by hand or by a jour fixe (see The standing meeting).
The schedule has three parts:
- Every
The period: hour, day, week, month, quarter or year, with “how many of them” beside it.
- Into the period
How far into the period the occurrence falls, in days, hours and minutes.
2dis the Wednesday of a weekly task, and2d 14his Wednesday at two.- Occurrences filed ahead
How far in advance the issues appear. Five weeks ahead means that the team can see and plan what is coming, instead of discovering it on the day.
Beside them, the task names the template that it files and has an
account of its own under Files them as. While that account is
disabled, the task files nothing, and the page says so. The issues
themselves are reported by a different account: the template’s owner,
which the template’s own page shows under Files them as. The status
that each issue starts in is set by the template, separately for each
issue of its tree, so a tree can arrive with its root at acknowledged
and its children at new.
A template whose root is a meta issue files a release (Developers), and only as an account that may file one in the project: a developer of a project that runs the compliance process. Where the template’s owner may not file a release, the task files nothing and its page says so, because a release filed as an ordinary issue would be wrong without anybody noticing.
Each occurrence files the template’s tree, with the deadline that each
issue carries counted from the occurrence (5d after it, say). The
template’s page lists everything that the template has filed, by hand
and on a schedule alike, and each issue that a task filed names the
template and the task that it came from. Switching a task off stops the
filing and removes nothing.
While a task has future issues that nobody has touched yet, its page
says how many and offers to close them (Close them). Do that before
you delete the task, because afterwards the issues no longer name it.
Deleting a task is always allowed: the issues that it filed stay exactly
where they are, stop naming a schedule, and keep saying which template
they are a copy of. What is refused is deleting a template while a
task or a jour fixe files it, because those would have nothing left to
file, and the refusal names them.
The filing is done by the server itself, so there is no cron entry to set up and nothing to forget on a new machine. Each occurrence is claimed once, so that two servers against one database, a restart or a clock that jumps cannot file one Wednesday twice.
Meetings#
Work is discussed before it is done, and much of what a tracker records is decided in that discussion. A meeting here is not a calendar entry with a tracker beside it: its agenda is issues, its invitees are accounts, its minutes are notes, and its hour goes on somebody’s timesheet like any other hour.
Figure 25 Meetings: what is coming up, and what has been.#
Meetings is in the menu of every page, beside Summary and
Roadmap, as soon as the installation holds one meeting. A tracker
whose projects never meet never shows the entry. My View also opens
with the next few meetings that you are invited to, how many days away
each one is, and whether it has an agenda yet.
Calling one#
A developer of the project may call a meeting. The form asks what the
meeting is about, when it starts, how long it lasts, and where it is: a
room, or a link beginning with http:// or https://, which
becomes the calendar entry’s URL. It also asks who is invited, from the
project’s members, and in which time zone the time is meant, so that a
change to or from daylight-saving time does not move the meeting. A new
meeting is Planned until its schedule is finished (below), and it is
then Agreed. A meeting can be marked private. It is then visible
only to its invitees, to whoever called it or runs it, and to the
project’s managers.
Figure 26 One meeting: the appointment, the agenda, the minutes, the invitees.#
The agenda#
The agenda is an ordered list of items, and an item is an issue or a
heading. Anybody who may see the meeting can propose an issue for
it, either with the box on the meeting page or with Discuss on the
issue itself. Whoever runs the meeting puts it on the agenda, rejects
it or defers it to the next meeting. Sort by priority orders the
agenda the way that the priority queue would.
Discuss on an issue leads to a page that lists the project’s meetings
that you can see, the latest fifty of them. There you can do two
things. For a meeting that is still Planned, you can propose the
issue for its agenda. For any meeting at all, including one that was
closed weeks ago, you can record that the issue was discussed there
(Record as discussed). That is what you want when you are writing up
afterwards what was settled where. The issue then names every meeting
that it is bound to, and says what each one is to it: the meeting that
it came out of, the meetings whose agenda it is on, and the meetings at
which it was discussed. Recording it needs no more than the right to
update that issue, and the same button takes the record back. The
meeting’s page lists the same issues under What it dealt with.
Finish the schedule ends the planning and makes the meeting Agreed:
every invitee is mailed the agenda, with a link for each issue and the
calendar entry attached. The agenda can be reopened, and the change is
mailed.
Skip it cancels one occurrence with a reason, and every item on its
agenda moves to the next meeting instead of being lost. If the schedule
had been finished, the invitees are told.
A meeting with nothing on its agenda reminds whoever runs it: once when it comes inside the reminder window (seven days by default), and then daily on the last day.
Holding it#
Enter meeting starts your clock on the meeting, because a meeting is
work, and it is charged like work, to the packages that the meeting
carries. Leave meeting stops the clock. The meeting itself keeps no
record of who was there or for how long: the run is the person’s, the
confirmation is the person’s, and the record is on that person’s sheet.
Until the meeting is closed, any invitee and whoever runs it may mark an
item Discussed, Done or Defer. That is how minutes actually get
written: by the people in the room as they go, rather than by one person
afterwards.
The minutes are entries that any invitee and whoever runs the meeting
may append, plus one main note that only whoever runs the meeting
writes, so that two people are never editing the same paragraph. An
entry about an issue on the agenda can be written onto the issue: it
becomes an ordinary note there, marked as written in this meeting, so
that the decision is kept with the work and not only in the minutes.
File a bug opens the report form for something that the meeting turned
up, and the new issue is recorded as having come out of the meeting.
Close the meeting makes the minutes and the outcomes final. It is
offered once the schedule is finished.
The standing meeting#
Figure 27 A jour fixe: the schedule, the fixed agenda, the default invitees, and the meetings it has made.#
A jour fixe is a standing appointment, and its schedule works like
the schedule of a periodic task: the same period, the same offset, the
same “how many in advance”. “Every Wednesday at 14:00, four meetings
ahead” is week, 1, 2d 14h, 4. Half past two is 2d 14h
30m, and 2d 14.5h says the same thing. The server makes the
meetings. Each meeting inherits the time, place, duration, responsible
person, invitees and private flag of the jour fixe, and may change any
of them for itself.
Occurrences still to come shows the schedule as it stands, a little
further ahead than the server makes meetings. The occurrences that
already have meetings are links to them, with their state and how much
is on each agenda. The ones that the server has not reached yet say so
and offer Create it now. Pressing that makes exactly the meeting that
the server would have made on the day, with the same invitees, the same
headings and the same checklists. That is how you set an agenda
further ahead than Occurrences filed ahead reaches. Pressing it twice
makes one meeting.
The agenda of a jour fixe is fixed in two ways, which are kept apart on purpose:
Standing headings: a line each, in order, such as “apologies”, “the budget” or “anything else”.
Templates on every agenda: templates whose issues are filed with each meeting and put on its agenda. A template that a periodic task files cannot be one of them. These are real issues, which can be assigned, estimated and timed, not headings. That is what makes “we always go through the open releases” a piece of work that somebody can be held to, rather than a line in a document.
Items that were deferred when no next meeting existed yet wait on the jour fixe, and are put on the next meeting that the server makes.
A jour fixe that has made meetings cannot be deleted; switch it off instead.
The plan#
The Summary menu has five tabs, and the summary’s filter applies to
all of them. Every bar, slice and band in them is a link into the
issue list that it counts.
Figure 28 Summary: MantisBT’s counts, by every field an issue has.#
Figure 29 Graphs: breakdowns, the trend, where the backlog sits, how long
issues stay in a status, and estimates against recorded effort.#
Graphs draws what the issues’ own history already holds, so it works
on data imported from before locust as well.
The breakdowns (by status, severity, priority, resolution, category and
developer) count the issues that are not closed. A tracker that has
been open for eight years has more closed issues than open ones, and a
bar that counts them says what the project used to be. By target
release is a breakdown that counts the closed issues as well, because a
release’s record is what it carried. It says so in a line of its own,
and its rows read newest release first, as a roadmap does.
By developer is divided further, into the statuses that the issues
are in. Twelve issues waiting to be reviewed and twelve waiting to be
started are the same count but not the same week’s work, and a plain
bar would make a person who was blocked look like a person who was
busy. Each band has the colour that its status has everywhere else,
and the whole bar is still one link into that person’s issues.
The other charts are about the history, so they count closed issues too: what was opened and finished, what stood where at the end of a period (an issue closed today was genuinely open last March), and how long the work took. They are these:
Opened and closed: how many issues were opened and how many were closed in each period.Open issues: the backlog at the end of each period, stacked by severity.Where the backlog sits: how many issues stood in each status at the end of each period.Days in a status: the median number of days that an issue spends in each status of the project beforeclosed. Every such status is shown, with zero where nothing has been measured yet.Estimates against the effort recorded, where a project estimates: for each developer, how far the effort recorded against their resolved issues missed the estimate, as the median of those issues. It is for making estimates better; it is not a scoreboard.Where a project allows fast-track: for each period, how many of the closed issues went the short way.
Summary and Graphs are both drawn from one database query, the most
expensive one on the tracker, and its result is kept for a day, so that
looking again costs nothing. Any change anywhere in the tracker
discards the kept result at once, on the server where it was made. So
the day only matters for what changes with the date alone, such as the
periods that the charts count in.
Figure 30 Gantt: the schedule that follows from the estimates, the
dependencies, the deadlines and people’s real availability.#
Gantt schedules forward from today. An issue starts as early as its
children allow, and as early as the person doing it has an hour to
spare. The date of each version is a line down the chart, so work that
crosses it will be late for that version, and a deadline is a mark in
the issue’s own band. There are three views: by release, one release,
or one row per person. Nothing here is saved: the chart is what follows
from the issues as they stand.
The chart covers today to a year from today, unless you give other dates in the two date fields. The view of one release covers today up to that version’s own date, so a bar that touches the right-hand frame is work that will not be done by that date. The window clips the drawing and not the schedule: the dates, the dependencies and the pile-ups are the same whatever you ask to see, and a bar cut by the frame is drawn with a square end to say that the work continues.
Issues without an estimate are drawn in no bar, and are listed beneath the chart with a link to each. That is the honest answer: a guess in a plan is read as a fact, so the plan says what it does not know instead.
In a compliance project the bar is longer than the estimate, because the estimate is the implementation, and the process also costs control, verification, deployment, release and communication. Those shares are the project’s setting, and they are drawn in a second colour.
Figure 31 Resources: planned hours against capacity, per person per week,
with the work nobody is named for in a lane of its own.#
Resources is the same schedule read the other way. For each person
it draws two lines, the hours planned and the hours available, per
week, month, year or decade (per week unless you choose otherwise). A separate
box, Work nobody is named for, shows the hours that the plan needs and
that no calendar carries.
The people who appear there are the ones whom the project offers for an
assignment, the members at handle_bug_threshold or above, apart
from administrator accounts. An administrator passes every threshold
in every project without being a member of any, so listing them would
put every administrator account in every project’s plan; those accounts
are for administering the tracker, not for being planned against.
Somebody who should be planned against needs an ordinary account. Work
that an administrator does hold is not hidden: it is drawn on the Gantt
chart like anybody else’s, and the schedule still books it. What
Resources has no row for is the administrator’s capacity.
A person’s capacity is built up in layers. The installation sets a
default of hours per working day. Each person’s own working weekdays
replace it, and the days that differ (leave, public holidays, half
days) replace those. Last, the project’s hours per person cap the
result: they say what a person gives this project out of their day,
and they never extend a day, so a day off stays off. People keep their
own weekdays and absences in their Availability tab, because they
know them best, and a manager of the project may edit them there too.
The project’s hours are yours to set.
Priorities is the queue of each person with its reasons
(Developers).
What somebody has on their plate. On My View and on the
Priorities tab, your name at the top left of the page is a list, where
you are a manager of the project chosen at the top of the page. Choose
a person from it, and the page is theirs: the issues assigned to them,
the estimates that are waiting for them, their queue, their deadlines,
and what they reported or monitor. The list offers the people who may
handle issues in the project, and under “All Projects” the people who
handle issues in any project that you manage. The page shows only what
you may read yourself, so an issue in a project that you are not in is
in none of their boxes. It leaves out their Right now box, their
running clock and their meetings, and the boxes that are not about them.
The address carries the person (my_view_page?user_id=N), so a link
to it can be sent; the My View entry in the menu is always your own.
You can also open a member’s queue from the project’s user list.
Release management#
A release is one issue: a meta issue, filed with the report form’s
Meta issue tick (“deployment only”). It starts in deploying, it
carries the issues that the release brings out as its children, and
while the release is being made, it is the only thing that anybody has
to touch. Any developer may file one, because it carries no change of
its own, so making one claims nothing. Putting a regular issue into
deploying is still your signature on a release, or that of a developer
whom the issue’s category ticks for Release signed by.
What the tracker refuses, and why:
A release does not leave
deployingwhile any of its children has not yet reacheddeploying, and the refusal names those children. The release depends on that gate: a record of a deployment that only partly happened would be a false record. Either bring the remaining children that far or detach them.MantisBT’s rule that a parent waits for its children does not apply to a release, and it cannot: it asks for every child to be resolved, which a child waiting to be deployed never is. The gate above replaces it.
A release is never a child, and nothing is attached to a release that has already gone out.
A release and one of its own children cannot be moved in one mass action, because releasing the parent is what moves the child.
When the release moves on, to verifying, informing or closed,
every child that is in deploying moves to verifying. Whoever
released it is recorded as the deployer, unless the plan already names
one, and the children appear on the assigned and unassigned lists
again. A release never goes back and is never reopened: the next
release is a new issue.
While a child is waiting behind a release, it has no handler, which is
deliberate: the release has it. So it is left out of My View’s
Unassigned box. The issue list behind that box’s heading is the
ordinary filter and still shows the child; that mismatch is known.
Work packages and budgets#
A work package is the contract or grant that hours are charged to:
one name that an auditor and a developer read the same way
(HORIZON-101234-WP2-Integration), with the granted hours, the dates
that it runs between, and whether it is still open.
An issue carries its packages, a checkbox each, and anyone who may update the issue may set them. The same bug is often one package for one person and another for the next, because what a funder paid for is the person’s time, not the bug. A meeting carries packages the same way.
Who may book to it, on each package, lists the people whose time may be booked to it. Nobody named means every member of the project, which is how every package starts, so a project that has not thought about eligibility works as if there were no such list. Somebody who has since left the project stays on the list, marked as gone: the list is a record of who was engaged, not a copy of the membership.Eligibility governs the booking, and nothing else. A reviewer who is on none of an issue’s packages may still review it, and you may still ask them to. What they cannot do is run a clock on it, and the refusal tells them to ask you.
A record keeps the package that it was confirmed against, and nothing moves it afterwards. A run divided between two packages writes one record per package per day, and the records of one day add up, to the minute, to what was measured that day.
A project that cannot accept unclassified hours sets
Classify before working. Then, when somebody takes an issue up, the tracker asks for the package first, and says which of two things is missing: nobody has classified the work, or nobody has engaged you on it. The bare timer (Start working) starts all the same, because not yet knowing what one is about to do is the reason it exists. What the setting refuses there is the confirmation, where the classification is made.Activity types are timed work that is no issue, such as a meeting, administration or training. Each run of one has its own package, chosen from the ones that the person may book to.
When you switch a package off, new work on it stops, nothing is removed, and you set for how many whole years its records must still be kept. If you give no number, the package keeps the figure that it had, or five years if it had none. When that time is up, the package appears on the list of packages due for deletion, which administrators see on
Manage Projects. Only an administrator may delete a package, and deleting it deletes the records booked against it. That andlocust retain(Administrators) are the only operations that delete records from a sheet that has been signed.
The timesheet (Developers) shows the hours per package per day, with what is left of each budget. A developer submits a month, and you approve it. Anything that changes in a submitted month makes the submission stale, and the month must be submitted again: that is what a signature on a document means.
Reporting to a funder#
A funder usually wants more than hours that exist somewhere: it wants
them reported, every month, quarter or year. Each work package therefore has a
Reporting page of its own, reached from its row on the Work packages
tab. The page has a schedule (monthly, quarterly or yearly, every n
of them, counted from a day that you give), the addresses that the
report goes to, what is waiting and what has been sent.
What the funder receives is the period, the package’s full name, the hours booked to it in the period, the hours since it began, the granted budget and what is left, as a plain-text table, with the same figures attached as a spreadsheet. No person, no issue, no day and no clock time are in it. That is why the address needs no vetting, why the data protection document (see What you may see, and what that costs) needs no new version, and why nobody has to be asked again. If a funder’s template asks for effort by name, that is a decision to take deliberately, with that document rewritten and signed again, and not a switch that anybody flips.
A report waits until every timesheet month that it reads has been
submitted and approved, because a figure that a funder files is a
figure that somebody has signed for. The page says which periods are
waiting and whose months they are waiting for. The people who still
have to submit are reminded as soon as a report is waiting for them, and
weekly after that, and so are you. Where one person never submits,
Release sends the period anyway. The mail then says that the period
was released and that the months of n people were not approved: a
count and no names, because the recipient is outside the tracker.
Pressing Release writes one line in the audit log.
A correction after a report has gone out puts the period back. The next
report of that period is marked as a correction and names the date of
the earlier mail and the difference, because the recipient’s file needs
a document that stands on its own; the Reporting page numbers the
reports in sequence. Nothing is ever sent twice for the same figure,
and a server that was switched off for two months sends both months
when it comes back.
What you may see, and what that costs#
A clock on a person is a monitoring system wherever it runs, and the tracker is built so that the decisions about it are visible rather than quiet:
A developer always sees their own sheet. A manager sees the rows of the projects that they manage, and one row with the person’s hours in all other projects together, per day. Asking for the issue-by-issue detail of somebody’s month is recorded, and that person can see that you asked. An administrator sees the whole sheet, detail included, without asking.
The whole manager’s view can be switched off for an installation (
timesheet_manager_view); a works agreement may draw the line exactly there. Approving a month needs that view, so with it off, the approval is given on the sheet that the person submits and hands over, and a report to a funder goes out only withRelease.The tracker never computes a utilisation percentage, never puts people’s hours side by side in a table, and never infers work from a commit, a login or an idle screen. Every number on a sheet is a clock that somebody started and ended deliberately.
A project records time once it runs the compliance process. The
obligations that this brings are real, the tracker cannot meet them for
you, and they apply before the measuring starts: co-determination where
it applies, telling each person before the measuring starts, and the
written data protection impact assessment that systematic monitoring of
people at work requires. docs/locust-legal.typ in the source tree
is the document that locust ships for the second of those.
Reports and exports#
Any filtered list exports as CSV or Excel, with the columns that
Manage Columnssets, and the print view also offers a Word document.A timesheet month exports as a monthly declaration (hours per work package, with the two signature blocks) or as a daily grid, with issue numbers only if asked for.
The summary tabs are pages, not exports. The lists behind every bar can be exported, because every bar is a link into the issue list.
Change LogandRoadmapare built from the fixed-in and target versions of issues; they are the reason to set those two fields with discipline.
What this tracker will not do#
This is written down here so that the next feature has to argue against a decision rather than merely add a column:
No table of hours per developer and no utilisation percentage.
No detection of presence, idleness or activity; no run started by a commit, a login or a window title; no screenshots.
No estimate that becomes a number in a plan without somebody standing behind it: work without an estimate is listed as such.